The system operator added that it promptly activated emergency response measures in line with established operational procedures.

“Preliminary reports indicate that the disturbance involved the tripping of several generating units and critical 330kV transmission lines, resulting in a widespread impact on electricity supply across parts of the country.

“However, the Delta generation complex successfully operated in island mode at the 132kV sub-transmission voltage level. This enabled the continued supply of electricity to Oghara, Amukpe, Benin, and Efunrun 132kV substations, with a total generation of 114 megawatts from four units at the Delta Thermal Power Station.

“In line with established Operational Procedures, NISO promptly initiated system response measures using its dispatch and monitoring tools at the National Control Centre in Osogbo,” the statement added.

NISO confirmed that electricity supply has now been fully restored nationwide, with system stability normalised after hours of coordinated recovery efforts.

“Supply has been fully restored to all parts of the country and the system stability normalised,” it stated.

The operator said investigations were ongoing to determine the precise cause and sequence of events that led to the partial collapse, assuring Nigerians that corrective measures would be implemented to prevent a recurrence.

“Investigations into the cause and sequence of events leading to the system disturbance are currently ongoing. Appropriate measures shall be put in place to forestall future recurrence of such major system incidents,” NISO said.

Grid collapses and system disturbances have remained a recurring challenge in Nigeria’s power sector, often triggered by gas shortages, weak transmission infrastructure and operational constraints.

Since the unbundling of the power sector, successive administrations have pledged reforms to stabilise the grid, improve gas supply to power plants and strengthen transmission capacity.

NISO, which recently assumed system operation responsibilities following power sector reforms, reaffirmed its commitment to proactive grid management.

“NISO reassures Nigerians of its continued commitment to proactive grid management and the application of best operational practices to ensure the stability and reliability of the National Grid,” the statement concluded.