Nigerians may celebrate the Yuletide in darkness if the Federal Government takes no further steps to defray the gas-to-power debt, as gas companies have begun cutting supplies to power plants, a development already affecting electricity generation nationwide.
On Tuesday, the Enugu Electricity Distribution Company informed customers across the South-East of the situation in a statement issued by its Group Head, Corporate Communications, Emeka Ezeh.
According to EEDC, the drop in power supply availability is due to low system frequency, said to have been occasioned by gas constraints affecting generation companies. The DisCo disclosed that the situation had necessitated load shedding of available energy by the Transmission Company of Nigeria.
As a result, EEDC said the development had impacted energy allocation to it and reduced the daily service level to customers served by its subsidiary companies — MainPower, TransPower, FirstPower, NewEra, and EastLand.
The statement read, “The Enugu Electricity Distribution Company PLC wishes to inform electricity customers across the South-East region that the recent drop in power supply availability is due to low system frequency, occasioned by gas constraints affecting the generation companies. This development has necessitated the load shedding of available energy by the Transmission Company of Nigeria.
“As a result, this development has impacted energy allocation to EEDC and the daily service level to customers served by its subsidiary companies, namely MainPower, TransPower, FirstPower, NewEra, and EastLand.
“Efforts are currently being made by critical stakeholders in the electricity supply industry to address this challenge and restore normal power distribution. EEDC sincerely apologises for the inconvenience this situation has caused its esteemed customers and appreciates their patience and understanding.”
Earlier, the Port Harcourt Electricity Distribution Company also issued a notice to customers, stating, “Dear esteemed customer, Kindly be informed that the current load shedding being experienced in all our franchise areas is a result of poor generation and allocation from the generation company and NCC.
“We appeal to our esteemed customers to exercise patience as the GenCo team is working assiduously to improve generation and allocation. All inconveniences are regretted.”
In an interview with our correspondent, generation companies confirmed that gas constraints were affecting their operations. The Chief Executive Officer of the Association of Power Generation Companies, Joy Ogaji, confirmed that gas producers had begun cutting supplies due to debts owed to them.
Recall that Nigerians experienced months of darkness in the first quarter of 2024 after gas companies stopped supplying feedstock to thermal power plants over unpaid debts. Although government intervention resolved the crisis at the time, gas producers said they have continued supplying gas without payment.
On December 4, 2025, the Federal Government announced the approval of N185bn for the payment of outstanding debts owed to natural gas suppliers in a bid to ease liquidity constraints and boost electricity generation nationwide.