The Federal Government has announced plans to revise the Lagos-Calabar coastal road project, reducing the number of lanes from 10 to six to cut costs.
The Minister of Works, David Umahi, disclosed this on Friday, December 20, during an inspection of the highway. He explained that the review was necessary due to design variations and additional interventions required for the project.
“This includes evacuation of refuse up to 10 meters deep and backfilling affected areas,” Umahi said
He added that efforts would be made to preserve some structures along the project corridor, with parts of the available land repurposed to accommodate a service lane for surrounding communities.
Umahi also highlighted the need to address gaps in the original design, including constructing a retaining wall in areas such as the Landmark section to ensure the project’s stability and longevity.
The revised 750-kilometre highway will feature solar-powered streetlights, security cameras, designated security points, and tree planting to enhance environmental protection and aesthetics.
“20 kilometres of the first section of the highway would be among other critical road projects scheduled for inauguration by May 29, 2026,” he stated.
The Lagos-Calabar coastal road project, originally estimated at N15 trillion, is to be executed by Hitech Construction Company, owned by Gilbert Chagoury, a long-time associate of President Bola Tinubu.
Spanning eight states along Nigeria’s coastal shoreline, the inter-state highway is designed as an economic corridor, beginning in Lagos State in the South-West and terminating in Cross River State in the South-South.
Despite its ambitions, the project has sparked intense debate, with critics questioning its necessity given Nigeria’s severe economic challenges.
One contentious issue is the compensation required for property owners along the corridor. The demolition of structures such as Landmark Beach Resort and other businesses in Lagos alone is estimated at over $200 million, further fueling concerns about the project’s viability.